Jordan Valley, UT
Date: 2020 – 2023
Client: Jordan Valley Water Conservancy District
AE2S completed the design for a new 51.7 MGD pump station to replace existing infrastructure and meet future projected demand. The new station runs in parallel with the existing facility, until the existing facility reaches the end of its useful life.
The electrical system of the new pump station consists of a 12.47kV backup generator, automatic transfer switch, a 4000kVA padmount distribution transformer, a 4.16kV medium voltage motor control center including electronic soft starters and VFDs, all required 15kV, 5kV, and other low voltage circuiting, lighting design, instrumentation and controls, and security systems. All electrical, instrumentation, and control design was performed in-house.
Electrical
Backup Power Generation
Motor Control
SCADA
Security
Lighting
More AE2S Electrical Projects
Services and Markets > Electrical > Pump Station Electrical System – Jordan Valley, UT